General planning and on-site construction supervision for the phased expansion of the Tulln Regional Hospital.
The expansion of the Tulln Regional Hospital took place in three construction phases. We managed the project as the general planner and as part of the on-site construction supervision team. The phased implementation required forward-looking planning, precise coordination, and special attention to the complex requirements of a hospital site.
Client
State of Lower Austria
Time period
April 2005 – September 2010
Location
Tulln
Status
completed
Scope of Work
General Planning, On-Site Construction Supervision | Planning through Design: Architects Loudon & Habeler

Construction Phase 1: April 2005 to September 2007
During the first construction phase, the Lower Austrian provincial government’s June 2002 decision to merge the two hospitals in Tulln and Gugging at the Tulln site was implemented. The new building, located in the eastern section and connected to the existing structure, houses the departments of neurology, inpatient psychiatry, child and adolescent psychiatry, psychotherapy, and physical therapy.
The northern section of the new building houses the new main entrance with the admissions area, reception desk, and service facilities such as a café, kiosk, hair salon, etc. Within the existing building, the operating room area, the imaging center, and the kitchen with dining hall were renovated.
In the southern section of the hospital grounds, the newly constructed training center began operations in December 2006.
Construction Phase 2: October 2007 to July 2008
On the north side of the existing building, a two-story addition and the adjacent renovation of the existing structure housed the interdisciplinary admission ward and the day clinic.
Construction Phase 3: September 2009 to September 2010